Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Road Construction in Bos en Dal

The resurfacing of Long Street, Bos & Dal will impact road users from 10 to 28 June 2024.

Project:
Resurfacing of Long Street, Bos & Dal

PLANNED CONSTRUCTION ACTIVITIES:
The works comprise the resurfacing of Long Street, Bos & Dal. The section in question is between Sysie Crescent and Union Street. Also included is the repair of damaged kerbs. The length of the above road section is approximately 880 meters. There is one lane in each direction along this section of the road, with numerous accesses to residential properties. The width of the road is approximately 8.0 meters.

PROJECT PERIOD:
10 to 28 June 2024.

SERVICE DISRUPTION:
Traffic congestion can be expected.

TRAFFIC IMPACT:
The remedial work will require the milling and removal of existing bituminous layers as well as the milling and removal of existing gravel base layers. After the milling operations, will follow the placing of new bituminous base layers and surface layers. The affected section/lane of work for the day will be closed to traffic. Traffic will be accommodated to flow with the assistance of Flagmen throughout the project. Work will commence at 8h00 each day and is envisaged to be completed by 17h00 each day.

DRIVING COMFORT:
There will be height differences between the two lanes while milling and asphalt construction work is in progress. Drivers, cyclists, and pedestrians must exercise extreme caution, especially during wet conditions and when visibility is poor and at night. Vehicles with low-profile tyres and motorcyclists must take extra care.

PROJECT ENQUIRIES: Willie Vogel – 082 799 8130

The George Municipality apologises for the inconvenience and appeals to road users to be patient and exercise caution during the project. Please look out for and adhere to temporary road signage and roadworks personnel.