PUBLIC NOTICE: Emergency Municipal Loadshedding Relief Grant APRIL 2023 Update
The Western Cape Provincial government has authorised a sum total of R88.185 million rand from the Provincial Unforeseen and Unavoidable Reserve Fund to assist municipalities with the unforeseen and immediate impact of prolonged load-shedding on water and wastewater services.
In terms of this allocated Funding, George Municipality has received the sum of R14 220 000 (VAT included) as a contribution toward the purchase and installation of back-up energy supply. This back-up supply can include generators, renewable power sources, batteries and all ancillary costs associated with the installation thereof for example, switch gear, safe keeping, caging etc. for water and wastewater infrastructure.
This grant funding will assist the George Municipality in ensuring a healthy environment and to continue with the provision of basic services to our citizens and businesses during the current load-shedding.
The municipality is in process of purchasing emergency diesel generators that will be placed strategically as follows:
Water Treatment Works
Haarlem WTW (+_ 150kVA diesel generator)
Uniondale WTW (+- 200kVA diesel generator)
Waste Water Treatment Works
Uniondale WWTW (+_ 200 kVA diesel generator)
Kleinkrantz WWTW (+_ 300 kVA diesel generator)
Outeniqua WWTW (+_ 1000 kVA diesel generator)
The municipality has to date (April 2023) completed the procurement of the contractors required to construct the Generators required for Haarlem and Uniondale water treatment facilities; and Uniondale and Kleinkrantz waste water treatment facilities. Due to the size of the Outeniqua wastewater treatment facility`s backup generator a separate procurement process had to be followed and is underway. A Professional Engineering Consultant was appointed to assist the George Municipality with the design, procurement and implementation of the backup generator units.
George Municipality has out of necessity already installed large generators at 30 Sewer Pump Stations and 5 at Water Treatment Works at a cost of approximately R52 million, in order to keep water flowing and sewerage pumpstations operational during loadshedding. A further 8 are in process of being procured at a cost of approximately R27 million rand and which includes the two 1250kVa for the Garden Route Dam. The costs of running these generators are exorbitant and currently totals approximately R148 000 per day in fuel alone at Stage 4, with the fuel costs even higher when Stage 5 and 6 are implemented.
Link to further information on how George Municipality is trying to mitigate the impact of load-shedding for George. https://www.george.gov.za/what-is-george-municipality-doing-to-alleviate-eskom-loadshedding-and-other-renewable-energy-projects/