Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Notices

PUBLIC NOTICE: Early Closure of MVR, DLTC and VTS offices

Please note both MVR’s, DLTC and VTS will close at 14:00 on Wednesday 17 April 2024, due to operational requirements.

Traffic Law Administration and Driving Licencing: 044 878 2400
Physical address Traffic and Licencing: Mission Street, Pacaltsdorp

Vehicle Licencing and Vehicle Testing Station: 044 801 9310
Physical address Vehicle Licencing: Hibernia Street, next to train station;

Blanco Bulk Office and Drive-through Vehicle Licencing: 044 801 9310/9311
Physical address: 9 George Road, Blanco

PUBLIC NOTICE: Easing of Water Restrictions from Level 2C to 2B

Special Council held on Friday 12 April 2024 resolved that, as of May 1, 2024, water restrictions in George will be eased from Level 2C to Level 2B. This means that emergency tariffs will no longer apply, and standard water tariffs will be charged.

Background
Stricter water restrictions were implemented in December 2022 due to the existing Water Treatment Works’ inability to meet the demand for drinking water. To address this, a temporary water purification package plant capable of treating 5Ml/day was installed. This plant served as a supplement during periodic shutdowns of the existing Water Treatment Works for maintenance, upgrades, and the ongoing construction of the new 20Ml Water Treatment Works plant.

Upgrades in Progress
The George Municipality received a Budget Facility for Infrastructure Funding (BFI) grant of R1.107 billion from the National Treasury in the 2021/22 financial year. The project, consisting of 12 different components, is expected to be completed within the next two years. The BFI project allows for the extension of George’s water treatment capacity over two phases spanning three years (2022 – 2025). Phase 2 entails an additional 20 Mℓ/day extension to the New George Water Treatment Works (WTW), and Phase 3 involves constructing an additional 30 Mℓ balancing dam at the New George Water Treatment Works (WTW).

The water restrictions imposed in December 2022 have been maintained up till now to manage the water demand, especially during frequent WTW shutdowns required for BFI construction. The package plant will continue operating until the completion, commissioning, and operation of the new 20Ml/day plant. The progress of the 20Ml/day extension will be reassessed again later this year, together with the possible impact of the seasonal peak for 2024/25 and the ongoing population growth in George taken into account. If necessary, stricter water restrictions will have to again be reintroduced.

Monitoring Raw Water Resources
Raw water resources, affected by increased demand and drier than usual conditions will continue to be closely monitored. Despite the Garden Route Dam being refilled to 100% capacity due to unusually heavy rainfall last week on April 9, this does not influence the decision to ease existing restrictions. Water remains a scarce resource that must be protected and preserved at all costs.

Level 2B Water Restrictions effective from May 1, 2024, in the George city area, and not in Uniondale and Haarlem:

1. The mechanical irrigation of gardens with municipal potable water is prohibited.
2. Gardens may be watered at any time using a handheld bucket.
3. Gardens may be watered using a handheld garden hose only within specified time frames.

  • From September 1 to April 30: 18:00 to 20:00
  • From May 1 to August 31: 17:00 to 19:00
  • For retirement villages and facilities: 16:00 to 18:00 throughout the year
  • Even numbered households: Mondays and Thursdays
  • Uneven numbered households: Tuesdays and Fridays4. The irrigation or watering of all sport fields is prohibited, except for specific instances.
    5. The washing of vehicles with a garden hose, except by commercial enterprises, is prohibited.
    6. The cleaning of ANY area by means of water is prohibited.
    7. The filling of swimming pools is prohibited, with exceptions subject to approved exemption applications.
    8. Where own water from a borehole or reservoir is used, appropriate notices shall be displayed.
    9. Applications for exemptions are to be submitted for approval.

Accident in Kaaimans Pass – Road partially closed

Issued by George Municipality, 14 April 2024, 16:27

A truck has overturned in Kaaimans Pass, Wilderness. Officials have closed one double lane, direction George to Wilderness. The second lane en route to George has been converted to a two-way traffic lane, vehicles traveling to and from George are not affected.

Traffic officials have been deployed to regulate the traffic flow. Further details will follow once we receive further updates.

ESKOM LOADSHEDDING UPDATE: 14 April 2024

After 18 consecutive days of no loadshedding, it will remain suspended until further notice. This positive development is attributed to the sustained availability of generation capacity and emergency reserves.

A total of 2 150MW of generation capacity is planned to be restored by Monday. Eskom will provide an update on Wednesday afternoon or promptly communicate any significant changes should they occur.

Tonight’s evening peak demand is 25 886MW. Unplanned outages were reduced to 12 850MW, while planned maintenance is currently at 7 368MW. (Eskom)

Planned Interruption of the Electricity Supply: Portion of Heather Park – Willow Road

THE FOLLOWING AREAS WILL BE AFFECTED:
PORTION OF HEATHER PARK – WILLOW ROAD.

NOTICE is hereby given that the electricity supply will be interrupted on WEDNESDAY 17 APRIL 2024 FROM 09H00 TO 16H30 to do alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.

Should circumstances prevent the work from being carried out during the abovementioned period; the work will be done on WEDNESDAY 24 APRIL 2024 FROM 09H00 TO 16H30.

*

BEPLANDE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER: GEDEELTE VAN HEATHER PARK – WILLOW ROAD

DIE VOLGENDE AREAS SAL GERAAK WORD:
GEDEELTE VAN HEATHER PARK – WILLOW ROAD.

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op WOENSDAG 17 APRIL 2024 VANAF 09H00 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op WOENSDAG 24 APRIL 2024 VANAF 09H00 TOT 16H30.

Planned Interruption of the Electricity Supply: Portion of Hoekwil

THE FOLLOWING AREAS WILL BE AFFECTED:
PORTION OF HOEKWIL
HOEKWIL RD, BOSBOK LINE ,GEELHOUT , HEIDE AVE, VALLEY, CHURCH RD, & PASTORIE LINE

NOTICE is hereby given that the electricity supply will be interrupted on SUNDAY 14 APRIL 2024 FROM 09H00 TO 16H30 to do alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.

Should circumstances prevent the work being carried out during the abovementioned period; the work will be done on SUNDAY 21 APRIL 2024 FROM 09H00 TO 16H30.

*

BEPLANDE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER: GEDEELTE VAN OF HOEKWIL

DIE VOLGENDE AREAS SAL GERAAK WORD:
GEDEELTE VAN OF HOEKWIL
HOEKWIL WEG,BOSBOK LYN ,GEELHOUT ,HEIDE LN ,VALLEY, CHURCH WEG & PASTORIE LYN

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op SONDAG 14 APRIL 2024 VANAF 09H00 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op SONDAG 21 APRIL 2024 VANAF 09H00 TOT 16H30.

Motor Vehicle Registration not operational on Saturdays Currently

 

Due to unforeseen circumstances, the Motor Vehicle Registation (MVR) next to the train station in Hibernia Street will not be operational on Saturdays for the foreseeable future. We apologise to the public for the inconvenience.

The operational hours at MVR in Hibernia Street are from 08h00 to 15h00 on weekdays. Contact MVR at 044 801 9310.
The Blanco MVR is also operational from 08h00 to 15h00 on weekdays. They have a drive through service for license renewals and do bulk dealer transactions.

Planned Interruption of the Electricity Supply: Portion of Denneoord

THE FOLLOWING AREAS WILL BE AFFECTED:
PORTION OF DENNEOORD – BERG STREET, WITLES AVENUE AND DARLING STREET.

NOTICE is hereby given that the electricity supply will be interrupted on SATURDAY, 13 APRIL 2024 FROM 09H00 TO 16H30 to do alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.

Should circumstances prevent the work from being carried out during the abovementioned period; the work will be done on SATURDAY, 20 APRIL 2024 FROM 09H00 TO 16H30.

*

BEPLANDE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER: GEDEELTE VAN DENNEOORD

DIE VOLGENDE AREAS SAL GERAAK WORD:
GEDEELTE VAN DENNEOORD – BERG STRAAT, WITLES LAAN EN DARLING STRAAT

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op SATERDAG 13 APRIL 2024 VANAF 09H00 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op SATERDAG 20 APRIL 2024 VANAF 09H00 TOT 16H30.