Eskom Loadshedding Update 21 January 2024
Whilst the Generation performance continues to improve, the heightened focus on planned maintenance and expected increase in electricity demand necessitates the implementation of Stage 2 loadshedding from 16:00 today until further notice.
George will be affected as follows:
Sunday 21/01/2024
None
Monday 22/01/2024
12:00 – 14:30
20:00 – 22:30
Tuesday 23/01/2024
20:00 – 22:30
Wednesday 24/01/2024
04:00 – 06:30
Thursday 25/01/2024
02:00 – 04:30
10:00 – 12:30
Friday 26/01/2024
10:00 – 12:30
18:00 – 20:30
Uniondale will be affected as follows:
Sunday 21/01/2024
16:00 – 17:30
Monday 22/01/2024
15:00 – 17:30
23:00 – 01:30
Tuesday 23/01/2024
23:00 – 01:30
Wednesday 24/01/2024
07:00 – 09:30
Thursday 25/01/2024
05:00 – 07:30
13:00 – 15:30
Friday 26/01/2024
13:00 – 15:30
21:00 – 23:30