ESKOM LOADSHEDDING UPDATE: 19 JULY 2023

ESKOM LOADSHEDDING UPDATE: 19 JULY 2023

Due to the breakdowns of eight generating units since Tuesday evening, Stage 4 loadshedding will be implemented from 16:00 today until 05:00 on Thursday. Thereafter, Stage 3 loadshedding will be implemented from 05:00 until 16:00.

Uniondale will be affected as follows:

Wednesday 19/07/2023
17:00 – 19:30

Thursday 20/07/2023
01:00 – 03:30
09:00 – 11:30
17:00 – 19:30

George loadshedding times for Wednesday, 19 July and Thursday, 20 July 2023 remain unchanged as follows:

Wednesday 19/07/2023
22:00 – 00:30

Thursday 20/07/2023
06:00 – 08:30
22:00 – 00:30