Eskom Loadshedding stage 4
Regretfully, Eskom has just been forced to implement Stage 4 loadshedding at 07:20 following Majuba Unit 5 and Tutuka Unit 4 tripping. A full statement will be published in due course.
Stage 4 to be implemented until further notice.
George will be affected as follows:
Tuesday 19/04/2022
14:00 to 16:30
22:00 to 00:30
Wednesday 20/04/2022
06:00 to 08:30
14:00 to 16:30
22:00 to 00:30
Thursday 21/04/2022
04:00 to 06:30
12:00 to 14:30
20:00 to 22:30
Friday 22/04/2022
04:00 to 06:30
12:00 to 14:30
20:00 to 22:30
Uniondale will be affected as follows:
Tuesday 19/04/2022
09:00 to 11:30
17:00 to 19:30
Wednesday 20/04/2022
01:00 to 03:30
09:00 to 11:30
17:00 to 19:30
Thursday 21/04/2022
07:00 to 09:30
15:00 to 17:30
23:00 to 01:30
Friday 22/04/2022
07:00 to 09:30
15:00 to 17:30
23:00 to 01:30
Issued by George Mun
19/4/2022 at 08:30