ESKOM LOAD SHEDDING UPDATE: GEORGE & UNIONDALE
ESKOM LOAD SHEDDING UPDATE: GEORGE & UNIONDALE
Issued by George Municipality 10/3/2022
Loadshedding will be reduced to Stage 3 from 21:00 tonight until 05:00 on Friday. Thereafter Stage 2 will be implemented until 05:00 on Monday, as previously communicated
George will be affected as follows:
STAGE 4
Thursday 10/03/2022
18:00 to 20:30
STAGE 3
Friday 11/03/2022
02:00 to 04:30
STAGE 2
Saturday 12/03/2022
02:00 to 04:30
10:00 to 12:30
Sunday 13/03/2022
08:00 to 10:30
16:00 to 18:30
Monday 14/03/2022
NONE
Uniondale will be affected as follows:
STAGE 3
Thursday 10/03/2022
21:00 to 23:30
STAGE 2
Friday 11/03/2022
05:00 to 07:30
Saturday 12/03/2022
05:00 to 07:30
13:00 to 15:30
Sunday 13/03/2022
11:00 to 13:30
19:00 to 21:30
Monday 14/03/2022
NONE