Eskom load shedding update – 12 January 2024

Eskom load shedding update: Stage 3 loadshedding will be implemented from 16:00 today (12 January 2024) with Stages 3 and 4 loadshedding being implemented over the weekend.
Issued by George Municipality 12 January 2024

George will be affected as follows:
Friday 12/01/2024
No further loadshedding

Saturday 13/01/2024
00:00 – 02:30
08:00 – 10:30
16:00 – 18:30

Sunday 14/01/2024
00:00 – 02:30
08:00 – 10:30
16:00 – 18:30

Uniondale will be affected as follows:

Friday 12/01/2024
No further loadshedding

Saturday 13/01/2024
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Sunday 14/01/2024
03:00 – 05:30
19:00 – 21:30