Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Notice Archive

Public Notice: Update on generators installed at Waste Water Treatment facilities

All the generators listed below were installed, tested and commissioned successfully except the generators for the Outeniqua Waste Water Treatment Facility.  The 650kva and 1000kva Generators at Outeniqua Waste Water Treatment Facility were delivered to the site in April 2024 and are under installation. The contractors are in the process of casting concrete plinths and installation of cabling from the generator positions to the motor control centres.  The project is scheduled for completion before the end of June 2024.

OVERALL PROGRESS TO DATE

Procurement Phase: 

Appointment of Consultant ( Complete ) – 100%

Appointment of Contractor: Haarlem WTW ( Complete ) – 100%

Uniondale WTW ( Complete ) – 100%

Uniondale WWTW ( Complete ) – 100%

Kleinkrantz WWTW ( Complete ) – 100%

Outeniqua WWTW ( In Progress ) – 100%

 

Construction Phase:

Haarlem WTW ( ± 150 kVA diesel generator ) – 100%

Uniondale WTW ( ± 200 kVA diesel generator ) – 100%

Uniondale WWTW ( ± 200 kVA diesel generator ) – 100%

Kleinkrantz WWTW ( ± 300 kVA diesel generator ) – 100%

Outeniqua WWTW ( ± 1 000 kVA + 650 kVA diesel generator ) – 75%

Public Notice: Premier to provide update on recovery efforts in George collapsed building tragedy

Premier Alan Winde and numerous role players will today give an update on the emergency response to the building collapse tragedy in Victoria Street in George.

Date: Friday, 10 May 2024
Time: 1:00 pm – 1:45 pm

Join online
Youtube:

https://www.youtube.com/@premieralanwinde

Facebook:

https://www.facebook.com/windealan

Twitter:

https://twitter.com/alanwinde

The Digicon will also be recorded and will be available on the Premier’s YouTube channel.

Planned Power Outage: Heather Park

NOTIFICATION OF THE INTERRUPTION OF THE ELECTRICITY SUPPLY.
THE FOLLOWING AREAS WILL BE AFFECTED: A PORTION OF HEATHER PARK, FIR ROAD AND YSTERHOUT STR

NOTICE is hereby given that the electricity supply will be interrupted on SATURDAY 11 MAY 2024 FROM 08H30 TO 16H30 for the purpose of doing alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.

Should circumstances prevent the work being carried out during the abovementioned period; the work will be done on SATURDAY 18 MAY 2024 FROM 08H30 TO 16H30
__________________________

KENNISGEWING VAN DIE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER.
DIE VOLGENDE AREAS SAL GERAAK WORD: GEDEELTE VAN HEATHER PARK FIR WEG EN YSTERHOUT STR

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op SATERDAG 11 MEI 2024 VANAF 08H30 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op SATERDAG 18 MEI 2024 VANAF 08H30 TOT 16H30

Planned power outage: portion of Pacaltsdorp

NOTIFICATION OF THE INTERRUPTION OF THE ELECTRICITY SUPPLY.

THE FOLLOWING AREAS WILL BE AFFECTED:

PORTION OF PACALTSDORP

BEACH RD, CHURCH RD, MISSION RD

NOTICE is hereby given that the electricity supply will be interrupted on SATURDAY 11 MAY 2024 FROM 08H30 TO 16H30 for the purpose of doing alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.

Should circumstances prevent the work being carried out during the abovementioned period; the work will be done on SATURDAY 18 MAY 2024 FROM 08H30 TO 16H30.

KENNISGEWING VAN DIE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER.

DIE VOLGENDE AREAS SAL GERAAK WORD:

GEDEELTE VAN OF PACALTSDORP

BEACH WEG, CHURCH WEG, MISSION WEG

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op SATERDAG 11 MEI 2024 VANAF 08H30 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op SATERDAG 18 MEI 2024 VANAF 08H30 TOT 16H30.

Unexpected Water Outage Delville Park

A faulty valve was found at Delville Park earlier today, and the George municipality team is currently on site to repair it. The estimated time for repair is 4-6 hours. Additionally, a water tanker is en route to Delville Park Primary School to provide temporary water supply.

UPDATE – GWAING RIVER, MOUTH AND BEACH REOPENED

Following the flooding incident several weeks ago which caused severe damage to the Blanco 350mm sewer line which transverses the Malgas River, the
Gwaing River, Mouth and Beach has been reopened for swimming and other water activities.

Interim repair measures have been implemented to half any further sewer spillage in the Malgas River.
The Civil Engineering Services department continues with the redesign of the support structure for the sewer line to accommodate the floodline and withstand future weather conditions.

Planned Power Outage: Thembalethu, Thursday 09 May 2024

NOTIFICATION OF EMERGENCY THE INTERRUPTION OF THE ELECTRICITY SUPPLY.

THE FOLLOWING AREAS WILL BE AFFECTED: PORTION OF THEMBALETHU, LIBODE, BIZANA, BHISHO, DIKELA, CALA, ZUSAKHE STREETS.

NOTICE is hereby given that the electricity supply will be interrupted on THURSDAY 09 MAY 2024 FROM 09H00 TO 16H30 for the purpose of doing alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.

Should circumstances prevent the work being carried out during the abovementioned period; the work will be done on TUESDAY 14 MAY 2024 FROM 09H00 TO 16H30.

***********************

KENNISGEWING VAN DIE NOOD ONDERBREKING VAN DIE ELEKTRIESE TOEVOER.

DIE VOLGENDE AREAS SAL GERAAK WORD: GEDEELTE VAN THEMBALETHU, LIBODE, BIZANA, BHISHO, DIKELA, CALA,
ZUSAKHE STRATE.

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op DONDERDAG 09 MEI 2024 VANAF 09H00 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op DINSDAG14 MEI 2024 VANAF 09H00 TOT 16H30.

Planned power outage: portion of Heatherlands

NOTIFICATION OF THE INTERRUPTION OF THE ELECTRICITY SUPPLY.
THE FOLLOWING AREAS WILL BE AFFECTED:
PORTION OF HEATHERLANDS
HILLWOOD RD, PLOVER RD AND MEADOW RD
NOTICE is hereby given that the electricity supply will be interrupted on WEDNESDAY 08 MAY 2024 FROM 09H00 TO 16H30 for the purpose of doing alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.
Should circumstances prevent the work being carried out during the abovementioned period; the work will be done on WEDNESDAY 15 MAY 2024 FROM 09H00 TO 16H30.

KENNISGEWING VAN DIE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER.
DIE VOLGENDE AREAS SAL GERAAK WORD:
GEDEELTE VAN OF HEATHERLANDS
HILLWOOD WEG, PLOVER WEG EN MEADOW WEG
KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op WOENSDAG 08 MEI 2024 VANAF 09H00 TOT 16H30 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.
Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op WOENSDAG 15 MEI 2024 VANAF 09H00 TOT 16H30.