NOTICE: ROADS AND STORMWATER UPGRADE BOB STREET

PROJECT DESCRIPTION: MIG Upgrading of residential streets and associated stormwater infrastructure servicing the Bob Street area in Thembalethu including Pitterson, Bob and Khululeka Streets.
PROJECT PERIOD: November 2021-April 2022
WORKING HOURS: Mondays to Fridays 07h00-18h00 and Saturdays when required.
TRAFFIC IMPACT:
Residents, road users and pedestrians must be cautious in the vicinity of roadwork sites for the duration of the construction period. Please adhere to flag persons, temporary road signage and markings.
ACCESS TO SITE:
Access to the site will be strictly controlled. Any member of the public who enters the site will have to comply with the relevant requirements in terms of the Health and Safety Act and National State of Disaster: COVID-19 Regulations.
PROJECT ENQUIRIES:
Benver Civils and Plant Hire (Pty) Ltd – Piet Combrink 076 392 9325