Public Notice: Update on generators installed at Waste Water Treatment facilities

All the generators listed below were installed, tested and commissioned successfully except the generators for the Outeniqua Waste Water Treatment Facility.  The 650kva and 1000kva Generators at Outeniqua Waste Water Treatment Facility were delivered to the site in April 2024 and are under installation. The contractors are in the process of casting concrete plinths and installation of cabling from the generator positions to the motor control centres.  The project is scheduled for completion before the end of June 2024.

OVERALL PROGRESS TO DATE

Procurement Phase: 

Appointment of Consultant ( Complete ) – 100%

Appointment of Contractor: Haarlem WTW ( Complete ) – 100%

Uniondale WTW ( Complete ) – 100%

Uniondale WWTW ( Complete ) – 100%

Kleinkrantz WWTW ( Complete ) – 100%

Outeniqua WWTW ( In Progress ) – 100%

 

Construction Phase:

Haarlem WTW ( ± 150 kVA diesel generator ) – 100%

Uniondale WTW ( ± 200 kVA diesel generator ) – 100%

Uniondale WWTW ( ± 200 kVA diesel generator ) – 100%

Kleinkrantz WWTW ( ± 300 kVA diesel generator ) – 100%

Outeniqua WWTW ( ± 1 000 kVA + 650 kVA diesel generator ) – 75%