UPGRADING OF SEWER NETWORK MEENT STREET

The upgrade of sewer infrastructure servicing Meent Street, Heather Park will have an impact on residents and road users for the estimated period from 11 September 2023 to 15 December 2023.

DESCRIPTION:
To accommodate current and future sewage flows a section of sewerage reticulation in Meent Street must be upgraded. The scope of works consists of trench excavations for the construction of a 400m gravity sewer pipeline.

PROJECT PERIOD:
11 September 2023 to 15 December 2023

SERVICE DISRUPTION:
Municipal services may be disrupted during construction. Advance notification of planned temporary disruptions will be sent out via social media. The contractor will communicate directly with residents regarding access to properties.

WORKING HOURS:
Working hours will be from 07h00 to 17h00 Mondays to Fridays and 07h00 – 14h00 on Saturdays as may be needed.
TRAFFIC IMPACT:
Residents, road users and pedestrians need to exercise caution throughout the duration of the construction period. Please adhere to flag persons, temporary road signage and road markings.
ACCESS TO SITE:
Access to the site will be strictly controlled. No member of the public will be allowed access to the construction area, in terms of the Occupational Health and Safety Act.

PROJECT ENQUIRIES: – WJ Civils attention Mr. Markus Du Plessis on 044 871 0414.

George Municipality apologises for the inconvenience and appeals to road users to be patient and exercise caution during the upgrade. Please look out for and adhere to temporary road signage and roadworks personnel.