ESKOM LOADSHEDDING UP DATE Monday, 04 September 2023 @18:50

 

With the increase in generation planned maintenance, as previously communicated and the loss of a further two generation units today, Stage 6 loadshedding will be implemented from 05:00 on Tuesday until further notice.

NUMBER OF AREAS REMAIN OFF DUE TO EXCESSIVE LOADING – 18H50
Please note that there are still quite a few areas off due to excessive loading. Areas will be restored as capacity becomes available.

George will be affected as follows:
Monday 04/09/2023
22:00 – 00:30

Tuesday 05/09/2023
04:00 – 06:30
12:00 – 16:30 **
20:00 – 00:30 **

Wednesday 06/09/2023
04:00 – 06:30
12:00 – 14:30
20:00 – 00:30 **

Thursday 07/09/2023
04:00 – 08:30 **
12:00 – 14:30
20:00 – 22:30

Friday 08/09/2023
04:00 – 08:30 **
12:00 – 16:30 **
20:00 – 22:30

Uniondale will be affected as follows:
Monday 04/09/2023
17:00 – 21:30 **

Tuesday 05/09/2023
07:00 – 09:30
15:00 – 19:30 **
23:00 – 03:30 **

Wednesday 06/09/2023
07:00 – 09:30
15:00 – 17:30
23:00 – 03:30 **

Thursday 07/09/2023
07:00 – 11:30 **
15:00 – 17:30
23:00 – 01:30

Friday 08/09/2023
07:00 – 11:30 **
15:00 – 19:30 **
23:00 – 01:30

Consumers are reminded to PLEASE use electricity sparingly when power returns after a 4-hour loadshedding slot. Please do not switch high-usage equipment on immediately after Loadshedding.

Consumers are urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding is scheduled to return. This will reduce the risk of overload tripping on the network.

Reporting power outages
Please do not phone the after-hours number or the Electrotechnical Department to report that you have no power immediately after load shedding is scheduled to be lifted. Please be aware of the rotational switching on i.e. areas are switched on one by one and not all at the same time to avoid overloading the system. Please wait at least 30 minutes before reporting no power. The Electrotechnical Directorate will be aware of a possible substation trip that needs to be sorted out.

Receive Eskom loadshedding notifications by downloading the free EskomSePush app from Google Play Store at https://sepush.co.za/