Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

PUBLIC NOTICE: Emergency Municipal Loadshedding Relief Grant August 2023 Update

The Western Cape Provincial government has authorized a sum total of R88.185 million rand from the Provincial Unforeseen and Unavoidable Reserve Fund to assist municipalities with the unforeseen and immediate impact of prolonged load-shedding on water and wastewater services.In terms of this allocated Funding, George Municipality has received the sum of R14 220 000 (VAT included) as a contribution toward the purchase and installation of back-up energy supply. This back-up supply can include generators, renewable power sources, batteries and all ancillary costs associated with the installation thereof for example,  switch gear, safe keeping, caging etc. for water and wastewater infrastructure. This grant funding will assist the George Municipality in ensuring a healthy environment and to continue with the provision of basic services to our citizens and businesses during the current load-shedding.

The municipality is in process of purchasing emergency diesel generators that will be placed strategically as follows:
Water Treatment Works

Haarlem WTW  (+_ 150kVA diesel generator)
Uniondale WTW (+- 200kVA diesel generator)

Waste Water Treatment Works
Uniondale WWTW (+_ 200 kVA diesel generator)
Kleinkrantz WWTW (+_ 300 kVA diesel generator)
Outeniqua WWTW (+_ 1000 kVA diesel generator)

Progress to Date:
A Professional Engineering Consultant was appointed to assist the George Municipality with the design, procurement, and implementation of the backup generator units.  The municipality has to date (August 2023) completed the procurement of the contractors required to construct the Generators required for Haarlem and Uniondale water treatment facilities; and Uniondale and Kleinkrantz wastewater treatment facilities.   Due to the size of the Outeniqua wastewater treatment facility`s backup generator a separate procurement process had to be followed and is underway.

It is furthermore to be noted that generator equipment in general is a long lead item, and therefore the delivery times associated therewith are very much dependent on the stock availability on same.    In this regard the major risk foreseen at this stage is a delay in timeous completion of the project because of the knock-on effect due external factors affecting and delaying the delivery time of equipment, i.e., shipping of imported components, strikes / shutdowns, etc, as well as any delay in the Outeniqua WWTW generator tender process.  In summary, the overall project progress is as follow:

Procurement Phase:   Appointment of Consultant ( Complete ) – 100%

  1. Appointment of Contractor: Haarlem WTW ( Complete ) – 100%
  2. Uniondale WTW ( Complete ) – 100%
  3. Uniondale WWTW ( Complete ) – 100%
  4. Kleinkrantz WWTW ( Complete ) – 100%
  5. Outeniqua WWTW ( In Progress ) – 80%

Construction Phase:   Haarlem WTW ( ± 150 kVA diesel generator ) – 80%

  1. Uniondale WTW ( ± 200 kVA diesel generator ) – 50%
  2. Uniondale WWTW ( ± 200 kVA diesel generator ) – 50%
  3. Kleinkrantz WWTW ( ± 300 kVA diesel generator ) – 60%
  4. Outeniqua WWTW ( ± 1 000 kVA + 650 kVA diesel generator ) – 0%

The total project expenditure to date (as at end of August 2023) is approximately 24.8% of the current funding allocation. Approval has been granted by the Western Cape Provincial Government for the rollover of funding to the 2023/24 financial year.

Other Load Shedding initiatives Implemented by George Municipality:
Battery energy storage is planned for all the Water and Waste-Water Treatment Plants as well as the Sewer Pump stations in order to reduce the diesel costs. The Battery Energy Storage System (BESS) deployment is being fast-tracked to save costs over the long run. The intention is to deploy BESS of more than 100MWh for the city using a phased-in approach. The city is currently in the process of feasibility studies for the BESS deployment, to assess the technical, environmental, economic and practical feasibility for installation and integration into the distribution network. These studies will further inform the city on the deployment strategy to undertake as it strives to reduce reliance from Eskom.

Link to further information on how George Municipality is trying to mitigate the impact of load-shedding for George. https://www.george.gov.za/george-municipality-installs-generators-to-protect-its-infrastructure-against-loadshedding/Regards