Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

NMB BULK WATER PIPELINE UPGRADE

The upgrade of the bulk water pipeline servicing Thembalethu, Parkdene and Lawaaikamp from the c/o Vuyani Ncamazana Street and Nelson Mandela Boulevard will have an impact on road users for the period from 09 July 2022 to 30 September 2022.

DESCRIPTION:

The existing bulk and distribution water pipeline servicing Lawaaikamp, Parkdene and Thembalethu from the c/o Vuyani Ncamazana Street, Main Street and Nelson Mandela Blvd, as well as portions of Stanford Mangaliso Street, will be upgraded.

PROJECT PERIOD:

09 July 2022 to 30 September 2022

SERVICE DISRUPTION:

To minimize disruption to traffic, construction work crossing Nelson Mandela Boulevard will be limited to night-time working (between 18h00 and 06h00). Municipal services may be disrupted during construction. Advance notification of planned temporary water and traffic disruptions will be sent out via social media.   Valve chambers will be constructed in the adjacent road reserve in this period as well.

TRAFFIC IMPACT:

The street will be partially closed to traffic during the construction period. Construction is planned for night-time operation to minimize traffic congestion. Extra care needs to be taken by road users and pedestrians throughout the duration of the construction period. Adherence to temporary road signage and markings will be required.

ACCESS TO SITE:

Access to the site will be strictly controlled. Any member of the public who enters the site will have to comply with the relevant requirements in terms of the Health and Safety Act.

PROJECT ENQUIRIES: WJ Civils, contact Wouter van Niekerk on Tel: 044 873 5798

The George Municipality apologises for any inconvenience and appeals to road users to be patient and exercise caution during the upgrade.

Please look out for and adhere to temporary road signage and roadworks personnel.